Canvas West | Construction update

21 September 2023

Want to learn about how construction is progressing at Canvas West in VIC? 
 
Several facilities are making significant strides, including National Tiles, Komatsu Australia, and Speculative Development 2A & 3A. 
 
At National Tiles & Spec 3A, progress includes the near completion of the office and warehouse structure, and the commencement of office glazing installation. External hardstands are also progressing well. 
 
Komatsu’s facility & Spec 2A are also making excellent progress. The warehouse, office roofs, and wall cladding are almost complete, and the internal warehouse slabs have commenced. In addition, the framing and rough-in work for the offices are in progress, with plans to start the office façade later this month. 
 
Canvas West’s infrastructure has also made great progress on the construction of Norah Court and Droomer Way which will enhance access to all facilities. 
 
We look forward to sharing more updates as the estate progresses. 
 
Learn more: 
www.CanvasWest.com.au 

Related News

07.05.26

FY26 half year results

Frasers Property Limited (FPL) has announced its results for the half year ended 31 March 2026 (1HFY26).

07.05.26

Australia's 1st: 3.0 star NABERS Embodied Carbon Rating

Our facility for Probiotec Multipack at The YARDS has been granted the first NABERS Embodied Carbon rating.

04.05.26

FlexCity redevelopment in Germany now complete

We have completed the redevelopment of our new premium industrial and commercial park, FlexCity, in Mülheim an der Ruhr.

17.04.26

The Anchor: Certified BREEAM-NL New Construction 'Excellent'

Our distribution centre at The Anchor, Lelystad in the Netherlands has achieved a BREEAM-NL New Construction ‘Excellent’ rating.

08.04.26

PIP ANZ opens new facility at The YARDS, NSW

PIP ANZ opens its new Western Sydney facility to provide efficient distribution for its national wholesale network.

It helps to stay informed and ahead.
Subscribe to our latest news.