Canvas West construction progress

31 October 2023

Our Canvas West estate in VIC is progressing well, with two roads and four facilities currently under construction. 
 
At an estate level, the initial two layers of asphalt have been successfully laid for Norah Court and Droomer Way, and the pedestrian walkway is now 50% complete. 
 
Komatsu Australia and Speculative Development 2A, are making great progress. Both warehouses are now fully enclosed, with internal concrete slabs complete, and preparations for the external concrete hardstand and carpark are underway. 
 
At National Tiles and its adjoining facility, the internal warehouse slabs are in the final stages of completion, and the outdoor spaces and hardstands are already taking form.  
 
We look forward to sharing more updates as the estate progresses. 
 
Learn more: 
www.CanvasWest.com.au

Related News

07.10.25

LINK set to be complete in Q1, 2026

We’re making excellent progress on LINK, our new industrial and commercial park in Günzburg, Bavaria, with completion scheduled for early 2026.

06.10.25

Helping Hands Day, Europe

The European team recently came together for our annual Helping Hands volunteering day, which embraces the chance to give back to local communities while strengthening team bonds.

01.10.25

Builder appointed to deliver three facilities at The YARDS

CIP Constructions has been appointed to deliver three facilities at The YARDS, Sydney.

23.09.25

Toshiba breaks ground at The YARDS

Construction begins on new facility for Toshiba Australia at The YARDS

23.09.25

Healthy Heads in Trucks & Sheds nutrition videos

Healthy Heads in Trucks & Sheds (HHTS), has created bite-sized nutrition videos

It helps to stay informed and ahead.
Subscribe to our latest news.